art_70__para__2
In the case of framework agreements concluded in accordance with Article 51, contracting entities shall not be bound to send a notice of the results of the procurement procedure for each contract based on that agreement. Member States may provide that contracting entities shall group notices of the results of the procurement procedure for contracts based on the framework agreement on a quarterly basis. In that case, contracting entities shall send the grouped notices within 30 days of the end of each quarter.